Study and design of 04 bulk product discharge hoppers of 50m3
Project duration: 08 months
Location: Autonomous Port of Dakar

TVS
Team and equipment mobilized
-
01 Project lead engineer
-
01 Steel Structure Manager
-
08 Boilermakers
-
08 Welders
-
04 Painters
-
04 Sanders
-
01 5T crane truck
-
01 Flatbed truck
Project stage
-
Computer-aided study and design
-
Definition of specifications
-
General drawing
-
Development of detailed plans
-
-
Prefabrication
-
Sandblasting and painting
-
Delivery on site
-
On-site assembly and testing